Flint misses new deadline in long-overdue lead line replacement effort

Flint misses new deadline in long-overdue lead line replacement effort
May 4, 2023 Bridge Michigan

By Kelly House Bridge Michigan

The Great Lakes News Collaborative includes Bridge Michigan; Circle of Blue; Great Lakes Now at Detroit Public Television; and Michigan Radio, Michigan’s NPR News Leader; who work together to bring audiences news and information about the impact of climate change, pollution, and aging infrastructure on the Great Lakes and drinking water. This independent journalism is supported by the Charles Stewart Mott Foundation. Find all the work HERE.


  • Flint originally agreed to finish replacing the city’s lead service lines by 2020
  • After multiple missed deadlines, a judge in February ordered the work completely done by August
  • Plaintiffs say the city is already missing deadlines related to that order

Two months after a judge ordered new deadlines for lead line replacement work that was supposed to be done three years ago, plaintiffs in a settlement with the city of Flint say the city has again fallen behind.

As Bridge reported earlier this year, up to thousands of Flint residents are still waiting for service line inspections or dealing with torn-up yards and sidewalks because work crews failed to clean up after past inspections.

As part of a 2017 settlement that Flint reached with city residents and advocacy groups (Concerned Pastors for Social Action, Flint resident Melissa Mays, the Natural Resources Defense Council and the ACLU of Michigan), the city was supposed to excavate some 31,500 service lines at Flint homes, and replace those that might contain lead by January 2020.

But that work has dragged on for years longer than it was supposed to, as Flint struggled against pandemic work stoppages, supply chain issues, trouble with contractors and recordkeeping lapses.

U.S. District Court Judge David M. Lawson in February set a new deadline of May 1 for Flint officials to figure out which properties are still damaged. Lawson gave the city until August 1 to finish the rest of the $97 million lead line replacement effort.

But Addie Rolnick, a Washington, D.C. based lawyer with the Natural Resources Defense Council, one of the plaintiffs, told Bridge that Flint has missed the May 1 deadline as well as a March deadline to conduct outreach to all residents still eligible for service line inspections.

“The city has mismanaged this program for years,” Rolnick said, and the latest setbacks are “deeply concerning.”

“There are residents who have been waiting years for the city to come back and repair their properties, who have really been in limbo,” Rolnick said.

Flint officials acknowledge they missed the deadlines, but city spokesperson Caitie O’Neill said the city is working to catch up and isn’t far behind.

“Our crews have doubled,” O’Neill said, “and they’re closing in on it.”

At the time of the February court order, plaintiffs estimated that about 1,000 Flint homes still needed their pipes checked for lead, and thousands more may be dealing with property damage from past excavations.

The lead line replacement effort is a crucial step in the city’s recovery from the Flint water crisis, which began in 2014 after a state-appointed emergency manager approved a disastrous switch of Flint’s water supply from Detroit’s system to the Flint River in a cost-cutting measure, without requiring anti-corrosion treatment.

The change in water chemistry allowed lead to leach from city pipes, prompting a crisis that grabbed national headlines and coincided with a Legionnaires’ disease outbreak that killed at least 12 people.

Although the city has since switched back to Detroit water, health experts advise Flint residents to drink only filtered water until all city lead lines have been replaced.

Rolnick said plaintiffs are “considering all options,” in light of the latest missed deadline.


Catch more news at Great Lakes Now:

Flush with cash, Michigan lawmakers try again to pass state septic code

Michigan brine brouhaha: Proposed limits for unpaved roads prompt dustup


Featured image: Flint has repeatedly missed deadlines to remove all lead service lines from the city’s water system. (Photo Credit: Bridge file photo)